House A-1
On fulfilled today:
- Completed installation of the 6th floor.
- It ends with installation of staircases and elevator shafts on the 5th floor
- Vedutsyaraboty on the device interior partitions on the 3rd floor
House Б-1
- Monolithic completed work on the basement floor.
House В-1
- The assembly of the 1st floor