Frosty winter continues in Ukraine. But we are constructing the first stage of the residential complex “New England against all the odds.
As of February 9, 2017 we have already built 12 floors in the building “Liverpool”, at this stage of construction we are working on the installation of the stairs to the 13th floor. One floor below we are working on the installation of ventilation units and elevator shafts of the 12th floor. Besides, we are carrying the installation of monolithic sites on the 11th floor, as well as demising and indoor walls on the 7th and the 8th floors.
Construction of the 5th floor is on the final stage in the building “Cambridge”. The ceiling and ventilation units of the 4th floor are in process of the installation. Moreover, we are working on the installation of monolithic ceiling areas of the 3rd and 4th floors and stairs to the 2nd, 3rd, and 4the floors.
The installation of the columns under the balconies and elevator shafts of the 3rd floor is continuing.
Construction of the 3rd floor of the building “Oxford” is on the final stage. Currently we are installing balconies on the 3rd floor and the stairs to the floor. We have already completed the installation of ventilation units of the 2nd floor.
The area for construction of the second stage of the residential complex “New England” is almost ready. We continue to dismantle the plant and carry out breakdown of the axes under the geology and parking.